WEEKS SEVENTY FOUR AND SEVENTY FIVE

By chepog

 

Wendera

 

Dsc_0099

Real progress has been made in the last two weeks, that the “pinhole” of light at the end of the tunnel – is getting brighter and brighter.

Week Seventy four’s focus was to paint the non-slip paint in all areas except the cockpit.  The cockpit will be done right at the very end.  The paint had finally arrived, and although it was a little darker than we had anticipated, we decided to proceed with a trial on the step hatches. The results were wonderful, and even Miss was pleased with the colour!  Always important to have the approval of a discerning woman!  The colour can best be described as a sandy colour, and we think it gives a lovely contrast to the glossy white.

Dsc_0009

The paint was rolled on and then sprayed with the non-slip particles (small beads of glass).  Then 24 hours later a second coat of the paint was applied.  Of course, the area first needs to be masked up.

The roof was next …

Dsc_0019

Then the top deck…

 Dsc_0012  Dsc_0010

Dsc_0017

The bathroom floors were painted with the glossy white non slip.

At the end of Week Seventy Four, with all the non-slip paint completed, there was a flurry of activity with the advantage of many helpers.  Sean tackled the engine room (again) …. and although he needs to contort to reach difficult areas, he is happy that it is almost completed.

            Dsc_0022 

Lorraine was given the task of modifying the mattress covers on the double bunks.  The ordered double mattresses needed customisation to fit in the boy’s bunks.

Dsc_0024

The hypervent was cut to size for the double bunks…

              Dsc_0065

The hypervent goes under the mattresses for ventilation.  The boys were then able to test out their new sleeping quarters ….

                    Dsc_0070

Deran was let loose installing the interior lights ….

                        Dsc_0025

Dsc_0026 Dsc_0067

The steering wheels were attached …. impressive …

Dsc_0011

The inverter-charger was installed the power panel in the port hull…

               Dsc_0013

While Ian (our resident expert qualified electrician) connected the power points.

All the doors were given their final painting….

Dsc_0007 Dsc_0008

A production line of doors.

The hand rails were attached…

              Dsc_0006

Week seventy five saw Chris hang all the doors, an enormous job ….

    Dsc_0014    Dsc_0069

                    Dsc_0015

Paul started constructing the templates for the laminate, for the saloon and galley bench tops …

Dsc_0075

and in both hulls …

     Dsc_0079 Dsc_0080 

Ben wanted a “feature” wall in his cabin, so that was masked up, painted and the interior light was installed.  The result is very classy…

       Dsc_0016 Dsc_0076

Paul modified the galley cupboard for the opening of the microwave and constructed and installed the shelf unit that the microwave will sit on …

         Dsc_0020

The guide handles and courtesy lights for the steps to the hulls were installed…

           Dsc_0093

And the fuel gauge installed above the inverter …

          Dsc_0086

Can you notice what Chris and Paul go up to on Friday?

Dsc_0099

The astute among you will notice the rudders have been removed.  This involved jacking Wendera up to take them out.  The rudders require a hole drilled in the shafts so the rudder tiller bars can be fitted.

And finally the hatches for each of the double cabins were installed, complete with their flyscreens… Ben helped with the installation …

          Dsc_0082

      Dsc_0091  Dsc_0092

 

   All signs are now pointing to the launch date being

Less Than 6 weeks